Concrete Calculator
Work out the cubic yards of concrete and the number of 60 lb or 80 lb bags needed for a slab, patio or walkway, with 10% extra.
What the concrete calculator does
Enter the length and width in feet and the thickness in inches. The tool returns the volume in cubic yards, the volume with 10% extra, and the number of 80 lb and 60 lb bags. A 10 ft by 10 ft slab 4 inches thick is 33.3 cubic feet, or 1.23 cubic yards. With 10% extra that is 1.36 cubic yards, or 62 bags of 80 lb mix.
The formula
Volume in cubic feet is length × width × thickness in feet. Because thickness is entered in inches, divide it by 12. Divide cubic feet by 27 to get cubic yards.
Why add extra
Ground is rarely perfectly level, forms bow slightly and some mix spills. Ordering about 10% more avoids a short pour. A short load leaves a cold joint, which is a weak line in the slab.
Bags or ready-mix
An 80 lb bag yields about 0.6 cubic feet and a 60 lb bag about 0.45. For small jobs such as a step or fence post, bags are practical. For slabs above roughly 1 cubic yard, ready-mix delivered by truck saves labour and gives a more even result. Trucks often have a minimum load and a short-load fee.
Choosing a thickness
Footpaths and patios are commonly 4 inches thick. Driveways that carry cars are often 5 to 6 inches, and heavy loads need more. Local building codes and the soil beneath decide the right specification, and a base of compacted gravel helps drainage.
Other shapes
For a round slab, area is π × radius squared. For a column, use the same volume idea with the circular area times the height. Add the pieces together.
This page is general information. Check local codes and ask a contractor for structural work.
Worked example: Pouring a 12 ft × 15 ft backyard patio slab at 4 inches thick
Suppose you are pouring a rectangular concrete patio measuring 12 feet wide by 15 feet long with a standard slab thickness of 4 inches:
- Step 1 — Convert thickness to feet: `4 inches ÷ 12 = 0.3333 feet`.
- Step 2 — Volume in cubic feet: `12 ft × 15 ft × (4 / 12) ft = 60.0 cubic feet`.
- Step 3 — Convert to cubic yards: Divide by 27 (`3 ft × 3 ft × 3 ft`): `60.0 ÷ 27 = 2.22 cubic yards`.
- Step 4 — Add 10% wastage buffer: `2.22 × 1.10 = 2.44 cubic yards` (66.0 cubic feet).
- Bag count if mixing by hand: At 0.60 cu ft yield per 80 lb bag (`66.0 ÷ 0.60`), you need 110 bags of 80 lb pre-mixed concrete (or 147 bags of 60 lb mix at 0.45 cu ft per bag).
Limits and what this tool cannot do
- Rectangular constant-depth slabs only: The formula (`L × W × T`) calculates flat rectangular pours. If your slab has thickened perimeter footing edges (monolithic turndown edges), cylindrical deck piers, or stepped stairs, calculate each rectangular section separately and add the volumes together.
- Does not engineer rebar, wire mesh, or subgrade base: Structural load capacity depends on soil compaction, crushed-stone subbase depth, concrete PSI rating (e.g., 3,000 vs 4,000 PSI), and steel reinforcement—none of which this volume calculator designs.
- Subgrade unevenness can exceed the 10% buffer: If a 4-inch trench is accidentally excavated to 5 inches deep across the middle, actual concrete volume jumps by 25%. Measure depth at several points across the form before ordering a ready-mix truck.
Frequently asked questions
How many bags of concrete are in a cubic yard?
About 45 bags of 80 lb mix, or 60 of 60 lb, before waste.
How thick should a patio slab be?
Usually 4 inches for foot traffic.
Do I need rebar?
Often wire mesh or rebar is used to control cracking. Ask your contractor.
Why does the tool add 10%?
To cover waste and uneven ground.
How many 80 lb bags of concrete make 1 cubic yard?
One cubic yard is 27 cubic feet. Because a standard 80 lb bag of pre-mixed concrete yields approximately 0.60 cubic feet when mixed with water, 1 cubic yard requires `27 ÷ 0.60 = 45` bags of 80 lb mix (or 60 bags of 60 lb mix).
How much does 1 cubic yard of wet concrete weigh?
Normal-weight portland cement concrete weighs roughly 4,000 to 4,050 pounds (about 2 US tons, or 1,815 kg) per cubic yard.
When should I order a ready-mix truck instead of buying bags?
Mixing more than 40 to 50 bags (roughly 1 cubic yard) in a portable wheelbarrow or drum mixer takes hours and risks part of the slab setting before you finish screeding. Above 1 to 1.5 cubic yards, ordering ready-mix concrete is usually faster and produces a stronger, continuous pour.